Starting Friday, Sept. 28, construction crews will be applying a microseal to the all roadways in Pajarito Acres and La Senda.
eather allowing, crews anticipate this portion of the project to last 11 days and crews are planning to work seven days a week from 7:30 a.m. to 5:30 p.m.
Representatives of IPR Limited, the contractor applying the coating, will be going residents door to door to disttibute information including the proposed schedule, coordination instructions and contact information.
The contractor is expected to start on cul-de-sacs in La Senda Friday followed by cul-de-sacs in Pajarito Acres Saturday and Sunday.
It is expected that the coating will cure enough to cross within 15 to 20 minutes and can accept full traffic 1 to 1-1/2 hours after the application is completed.
During the application of the microseal on the roadways other than cul-de-sacs, one lane will be closed allowing for one way traffic via a flagging operation. Cul-de-sac work will require an entire road closure and work will be coordinated with the affected residents.
Questions or comments regarding this project may be directed to Anthony “Hawk” Trujillo at 505.662.8113 or 505.500.5658 or via email at anthony.trujillo@lacnm.us. Frank Clark, the contractor representative for IPR, Limited may be contacted at 505.362.8898 or via email at fclarkipr@gmail.com.